快速项目质量保证:上线前的三次验收
文章目录
短期(2-4周)项目要保证保证进度和质量,保证上线版本与设计一致,最有效的方法就是进行定期验收。
下面给出我的建议方案:
1tracer (overwatch), (visor, googles),brown eyes, short brown hair, cropped jacket, orange leggings, looking at viewer, smiling, teeth, standing, from_behind, upper body shot, outside, city alleyway, graffiti, blue sky, high quality, masterpiece, <lora:OverWatch_Tracer-DEF:.7>
2Negative prompt: fcNeg-neg, EasyNegativeV2, verybadimagenegative_v1.3
3Steps: 30, VAE: vae-ft-mse-840000-ema-pruned.ckpt, Size: 1024x1536, Seed: 1428282915, Model: realcartoonPixar_v10, Version: v1.7.0, Sampler: DPM++ 2M SDE Karras, CFG scale: 6, Clip skip: 2, TI hashes: [object Object], Model hash: 0f1bab0873, ControlNet 0: [object Object], Denoising strength: 0.22, Ultimate SD upscale padding: 32, Ultimate SD upscale upscaler: 4xUltrasharp, Ultimate SD upscale mask_blur: 8, Ultimate SD upscale tile_width: 512, Ultimate SD upscale tile_height: 512
项目上线前,必须包含以下三个版本。
- A 核心玩法DEMO(会议验收:项目组全体)
- B 主要玩法实现60%(会议验收:项目组全体)
- R 提审前完整版(会议验收:项目组+发行)
版本A:核心玩法DEMO
完成内容:
- 仅包含核心玩法界面,没有其他界面;
- 核心玩法的UI界面完整;
- 所有与核心玩法相关的素材完整;
- 如有动画、特效,需要实现1-2个,要求能表现出核心玩法的基础体验;
- 不必包含音效、音乐;
验收内容:
- 美术是否符合设计方案;
- 动画、特效是否符合预期;
- 核心玩法体验是否符合预期;
- 产品运行性能是否合理。
版本B:主要玩法实现60%
完成内容:
- 主要界面和逻辑均已实现;
- 游戏内容完成度超过60%;
- 音乐音效均已加入;
- 允许缺少部分内容,允许锁定部分交互按钮。
验收内容:
- 美术是否是符合设计方案;
- 动画、特效完整、合理、可用;
- 音乐和音效与游戏本体风格匹配;
- UE合理;
- 数值体验合理;
- 商业化逻辑合理。
版本R:提审前完整版
所有内容均已完成,待提审。
验收内容:
- 数值完整体验;
- 商业化完整体验;
- 项目团队与发行团队对齐产品预期。
更多版本
如果需要更细节的版本控制,可以阅读我这篇10年前的文章:项目版本描述规则
全文完
- 文章ID:2826
- 原文作者:zrong
- 原文链接:https://blog.zengrong.net/post/three-inspections-before-going-live/
- 版权声明:本作品采用 署名-非商业性使用-相同方式共享 4.0 国际 (CC BY-NC-SA 4.0) 进行许可,非商业转载请注明出处(原文作者,原文链接),商业转载请联系作者获得授权。